Successful Projects

Feasibility Study for Haoqin No 1 Mine

Time :2010-8-13
Haoqin No 1 Mine
Initial Feasibility Study Report for Haoqin No 1 Mine, Xiwuzhumuqin Banner, Inner Mongolia
Location: Xuejiawan, Zhunge’er Banner, Ordos, Inner Mongolia
Construction Size: 4.00Mt/a
Exploitation: Using single level mine shaft opening, fully mechanized coal mining method full seam recovery
Construction Period: 35 months, (under construction)
Coal Type: middle moisture, middle ash, low sulfur, mid calorific value thermal coal

Feasibility Study for Yuanbao Mine & CPP

Time :2010-8-13
Yuanbao Mine Shaft
Project: Feasibility Study Report for Yuanbao Mine Shaft and CPP, Shanxi Yuanbao Energy Development Co. Ltd.
Location: Yuanbaozi, Youyu Town, Shouzhou City, Shanxi
Construction Size: 3.00Mt/a
Exploitation: inclined shaft, multi-level mine shaft opening, coal caving mining method and fully mechanized coal mining method with full seam recovery
Construction Period: 26 months, was put into production in Dec 2009
Coal type: middle ash, low sulfur, middle-high calorific value lignite, used for civilian and thermal power.

Feasibility Study for A’rgongqu No 1 Shaft

Time :2010-8-13
A’ergongqu No 1 Shaft
Project: Feasibility Study Report for A’ergongqu No 1 Shaft, Beijing Energy Investment (Group) Co. Ltd.
Location: New Bar Tiger Left Banner, Hulunbeir, Inner Mongolia
Construction Size: 5.00Mt/a
Exploitation: inclined shaft, multi-level opening, using coal caving mining method
Construction Period: 22 months, (under construction)
Coal type: lignite, coal seam is special low sulfur, low phosphorus, low ash, middle-low calorific value, can be use as thermal power or as conversion to oil.

Feasibility Study, Manlailiang Mine

Time :2010-8-13
Manlailiang Underground Mine
Project: Feasibility Study Report, Manlailiang Mine Shaft, IMengtai Coal and Power Group Co. Ltd. Inner Mongolia
Location: Nalintaohai Town, Yijinhuoluo Banner, Ordos City
Construction Size: 1.80Mt/a
Method of Exploitation: inclined shaft, multi-level opening. Fully mechanized coal mining method, full seam height recovery.
Construction Period: 24 months, into production in April 2011
Coal type: Low – high ash, low – middle-high sulfur, low – mid level Phosphorus, high calorific value non-coking coal. Good thermal coal quality, also suitable for cement and chemical industries.

Feasibility Study Report for Hongtonghao Mine

Time :2010-7-29
Hongtonghao Mine
Project: Feasibility Study Report for Hongtonghao Mine, Taixin Coal Co. Ltd., Ordos
Location: Yijinhuoluo Banner, Ordos
Construction Size: 5.00Mt/a
Exploitation: mixed opening inclined and vertical shaft, fully mechanized coal mining method full seam recovery
Construction Period: 25 months, (under construction)
Coal Type: low – middle moisture, special low ash – low ash, special low sulfur – low sulfur, special low Phosphorus – low Phosphorus, high calorific value non-coking coal. Good quality thermal power coal suitable for industrial boilers, steam engines, cement making and chemical industry.

Initial Design for Aiminwendu Mine

Time :2010-7-29
Aiminwendu Mine
Project: Initial Design for Aiminwendu Mine, Tianshan Coal Chemical Co. Ltd., A’lukerqin Banner
Location: Shaogen, A’lukerqin Banner, Chifeng City, Inner Mongolia
Construction Size: 1.20Mt/a
Exploitation: Using multi-level mine shaft opening, fully mechanized coal mining method full seam recovery
Construction Period: 26 months, was put into production in Dec 2009
Coal Type: middle ash, low sulfur, middle – high calorific value lignite, used for civilian and thermal power coal.

Bayanbaolige No 1 Mine and CPP Design

Time :2010-7-29
Bayanbaolige No 1 Mine and CPP
Project: Bayanbaolige No 1 Mine and CPP Design, Xiexinxilin Mining Co. Ltd., Inner Mongolia
Location: Bayanbaolige, north of Xilinhaote City, Inner Mongolia
Construction Size: 8.00Mt/a
Exploitation: Using multi-level mine shaft opening, coal caving mining method and fully mechanized coal mining full seam recovery
Construction Period: 32 months, (under construction)
Coal Type: middle ash, low sulfur, middle-high calorific value No 2 lignite, used for civilian and thermal power, or coal gasification.

Initial Design for Saimengte’er Mine, Ordos

Time :2010-7-29
Saimengte’er Mine Shaft
Project: Initial Design for Saimengte’er Mine, Saimengte’er Agriculture Comprehensive Development Co. Ltd., Ordos
Location: Ordos, Inner Mongolia
Construction Size: 1.50Mt/a
Exploitation: inclined shaft, single level opening. Using fully mechanized coal mining method full-seam recovery
Construction Period: 18 months, (put into production in Nov 2009)
Coal Type: middle- high calorific value, special low sulfur, special low - low burning point, non-coking coal. Widely used for civilian and thermal power generation.

Feasibility Study Report for Boligou Mine and CPP

Time :2010-7-29
Boligou Mine and CPP
Project: Feasibility Study Report for Boligou Mine and CPP, Inner Mongolia Energy Power Investment Co. Ltd.
Location: Xuejiawan, Zhunge’er Banner, Ordos City, Inner Mongolia
Construction Size: 4.00Mt/a
Exploitation: mine shaft, single level opening, using coal caving mining method
Construction Period: 36 months, (in progress)
Coal type: low sulfur, low Phosphorus, high ash, middle – high calorific value coal.
Good thermal power coal, also suitable for industrial boilers, and also can be used for cement manufacture and chemical industry.

Initial Design for Dongping Underground Mine Shaft

Time :2010-7-29
Dongping Mine Shaft
Project: Initial Design for Dongping Mine Shaft, Beilian Electric Energy Development Co., Ltd, Inner Mongolia
Location: Jinlingaole Town, West Ujimqin Banner, Inner Mongolia
Construction size: 10.00Mt/a
Method of exploitation: Using multi-level mine shaft opening, fully mechanized coal mining method full seam recovery
Construction period: 32 months, (under Construction)
Coal type: low – middle moisture, low ash – low-middle ash, low sulfur, high Volatility, low Phosphorus, middle – high calorific value

Completed Projects